Take the Pex tubing and evenly place it as coils across the ground where you will pour your slab. Run it down one length, around the corner and back up the other side. Repeat this process until the ground is covered. Stay away from the edges of the room by 6 inches.
Spray an oxygen barrier on the Pex tubing to protect the heating system from getting any oxygen inside, which can cause deterioration.
Place a metal hose anchor over the tubing every 12 inches. The half-circle supports have flanges on both sides that screw into the ground to hold the tubing in place.
Place a metal rebar grid over the tubing. The rebar rods are placed in a way to form a checkerboard appearance over the slab area. Tie the rebar with tie wire at each intersection.
Pour your concrete over the ground to create your concrete slab. Cover the tubing completely.