Collect the drawings that show the foundation work, including the plan, the section and elevation, and the details. Review general conditions, special conditions and construction contracts first, and then check responsibilities and overlapping tasks.
Assemble plan views of foundation and site work. Keep the list of symbols close at hand for reference. Study the drawings in order of construction sequence.
Study the site plan for topography, site conditions and as a reference for foundation layout. Look at the foundation plan for layout and dimensions of footings and foundation walls, and for the relationship of the foundation elements with structural framing members. Note drainage and waterproofing details.
Gather vertical information from section, elevation and detail drawings. Note connection and reinforcement details. Cross-reference with plan views for a comprehensive understanding of the sequence of work. Examine where foundation work intersects with other trades.
Review project specifications for information about subgrade preparation, concrete mix design and finish quality. Check shop drawings appended to the specifications for reinforced steel size, grade and spacing. Note locations for concrete joint placement in the shop drawings.
Study the milestones in the schedule for inspection duties. Organize any discrepancies noted and any points that need clarification, and raise the issues with the appropriate authority.